Mining notification - General managers & production managers
Reference should be made to the appropriate section Mines Inspection ACT 1901 and General Rule 2000 for further information.
EVENT |
NOTIFICATION TO INSPECTOR |
REFERENCES |
|---|---|---|
Nomination of general manager |
Written - owner must notify the Chief
Inspector through your local office as soon possible. |
|
Appointment of production manager (not required for exploration) |
Written - as soon as possible to the
Chief Inspector. |
|
Appointment of unqualified production manager (not required for exploration) |
Written - to the Chief Inspector. |
Page: 5.24
Commencement of Mining, Abandonment, Recommencement, Change of Mine Name, Ownership and Company Officers
Reference should be made to the appropriate section Mines Inspection ACT 1901 and General Rule 2000 for further information.
EVENT |
NOTIFICATION TO INSPECTOR |
REFERENCES |
|---|---|---|
Supply of plans & sections of abandoned mine |
Within three months - supplied to the
Minister. |
|
Notification of commencement of shaft sinking, tunnelling or quarrying |
Written within 14 days |
|
Notification of abandonment or discontinuation of operations (total or in part) of a mine |
Written within 14 days |
|
Notification of recommencement of work after abandonment or discontinuation |
Written within 14 days |
|
Notification of changes of: Mine name Owner or general manager Principal officers of any company which is the owner of the mine. |
Written within 14 days |